On a patch of Atlantic Ocean floor 3.8 miles southeast of Block Island, Rhode Island, workers began preparing the seabed for something the United States had never seen before: a commercial offshore wind farm. It was 2015 C.E., and after years of permitting battles, legal challenges, and engineering simulations numbering in the millions, the country’s first offshore wind project was finally moving from blueprint to reality.
Key facts
- U.S. offshore wind farm: The Block Island Wind Farm consists of five Alstom Haliade 150 turbines, each rated at 6 megawatts, producing a combined 30 MW — enough to generate more than 125,000 megawatt-hours of electricity annually.
- Offshore construction timeline: Steel foundation work began at a Houma, Louisiana shipyard in late 2014 C.E., and the first foundation began its barge journey to Rhode Island on June 26, 2015 C.E. — marking the physical start of construction at sea.
- Grid connection cable: Power travels from the turbines through a 21-mile submarine cable buried under the Atlantic Ocean floor, making landfall near Scarborough Beach in Narragansett, Rhode Island — the longest buried offshore power cable in the U.S. at the time.
Why it took so long to get here
The road to 2015 C.E. was anything but smooth. Deepwater Wind, the project’s developer, had been working toward this moment since at least 2009 C.E., when Rhode Island designated it to begin pilot offshore wind development. What followed was a years-long maze of regulatory fights.
The Rhode Island Public Utilities Commission initially rejected the power purchase agreement with National Grid, calling the price — 24.4 cents per kilowatt-hour — excessive for ratepayers. The state legislature and governor changed the law to allow approval. Opponents then appealed to the Rhode Island Supreme Court, which upheld the contract in 2011 C.E. Additional complaints were filed with the Federal Energy Regulatory Commission in 2012 C.E. and again in May 2015 C.E., just as construction was beginning. Deepwater Wind dismissed both.
Nine separate permits from state and federal agencies were required before a single foundation could move. The last permit arrived in early May 2015 C.E.
Engineering a first
The turbines — each standing 600 feet tall — were designed to withstand a Category 3 hurricane. But the foundations holding them to the seafloor required an entirely different kind of engineering. Louisiana-based Keystone Engineering Inc. designed four-pile jacket foundations, a structure borrowed from offshore oil and gas platforms, and then adapted it to handle the continuous vibration and dynamic loading that spinning wind turbines produce. The team ran nearly 10 million test simulations before finalizing the design.
That borrowing from oil and gas expertise was no accident. Louisiana offshore service providers played a central role in making the project possible. Gulf Island Fabrication built the steel foundations in Houma. Falcon Global’s lift barge “The Robert” traveled roughly 2,000 miles from Louisiana to Block Island over 14 days to assist with offshore installation. The energy transition, at least here, was built in part by workers whose careers had been shaped by fossil fuel infrastructure.
Financing for the $290 million project came from two mandated lead arrangers: Société Générale of Paris and KeyBank National Association of Cleveland, Ohio — a transatlantic financial partnership that reflected both the novelty and the ambition of the undertaking.
What it meant for Block Island
Block Island, also known as New Shoreham, had never been connected to the mainland power grid. Its electricity came entirely from diesel generators — noisy, polluting machines that fouled the air and cost residents some of the highest electricity rates in the country. The wind farm’s 21-mile submarine cable would connect the island to the grid for the first time in its history.
When the turbines finally came online in December 2016 C.E., residents noticed the silence first. The generators were gone. Soot that had been dirtying curtains stopped accumulating. Birdsong returned. And electricity costs dropped by roughly one-third. For a small island community, those were not abstract environmental benefits — they were immediate and daily.
Lasting impact
Block Island Wind Farm did not generate much electricity in the national context. Thirty megawatts is a small fraction of U.S. power capacity. What it generated instead was proof: that offshore wind was buildable in American waters, that the engineering could handle Atlantic conditions, that the permits could be won, and that communities could benefit directly.
That proof mattered. The years after 2015 C.E. saw a wave of offshore wind development proposals along the U.S. East Coast — projects measuring in the hundreds and eventually thousands of megawatts. Deepwater Wind itself was acquired by Ørsted, the Danish energy company that had pioneered offshore wind in Europe, and rebranded as Ørsted US Offshore Wind. The U.S. Bureau of Ocean Energy Management expanded its offshore wind lease program substantially in the years following. By the early 2020s C.E., the U.S. had committed to 30 gigawatts of offshore wind by 2030 C.E. — a goal that traces at least part of its lineage to five turbines off a small Rhode Island island.
The project also demonstrated a model: that offshore wind development could double as grid infrastructure for underserved or isolated communities. That lesson has since informed proposals for island and coastal communities in other parts of the country and the world.
Blindspots and limits
The Block Island Wind Farm was not without complications. By 2021 C.E., four of the five turbines had been taken offline for at least two months due to turbine stress fatigue and erosion that exposed the underwater transmission cables — problems that raised real questions about maintenance costs and long-term durability for offshore infrastructure in harsh Atlantic conditions. The power purchase agreement that made the project financially viable also locked Rhode Island ratepayers into electricity prices with a guaranteed 3.5% annual increase, a tradeoff that generated controversy throughout the approval process and beyond.
The project also relied heavily on foreign vessels and equipment — including a Norwegian jack-up installation ship and French-manufactured turbines — because U.S. maritime law, specifically the Jones Act, restricts the use of foreign-flagged vessels in domestic waters, a constraint that added logistical complexity and cost. Building a robust domestic offshore wind supply chain remained an unresolved challenge for the U.S. industry long after Block Island’s turbines started turning.
Read more
For more on this story, see: Block Island Wind Farm — Wikipedia
For more from Good News for Humankind, see:
- Renewables now make up at least 49% of global power capacity
- Indigenous land rights recognized for 160 million hectares at COP30
- The Good News for Humankind archive on renewable energy
About this article
- 🤖 This article is AI-generated, based on a framework created by Peter Schulte.
- 🌍 It aims to be inspirational but clear-eyed, accurate, and evidence-based, and grounded in care for the Earth, peace and belonging for all, and human evolution.
- 💬 Leave your notes and suggestions in the comments below — I will do my best to review and implement where appropriate.
- ✉️ One verified piece of good news, one insight from Antihero Project, every weekday morning. Subscribe free.
More Good News
-

China plans to double its already massive clean energy supply by 2035
China’s new climate pledge to the United Nations sets a target of 3,600 gigawatts of wind and solar power by 2035 — more than the entire electricity-generating capacity of the United States today, and roughly double what China has already built. The commitment is woven into the country’s next Five-Year Plan, which directs state banks, provinces, and manufacturers to move in the same direction. Because China makes about 80% of the world’s solar panels, every factory it scales up makes clean energy cheaper for buyers in Africa, Southeast Asia, Latin America, and everywhere else. That ripple effect is what makes…
-

Doctors hail first breakthrough in asthma and COPD treatment in 50 years
Benralizumab, a single injection given during an asthma or COPD attack, outperformed the steroid pills that have been the only emergency option since the 1970s. In a King’s College London trial of 158 patients, those who got the shot had four times fewer treatment failures over 90 days, along with easier breathing and fewer follow-up visits. Because steroids carry real risks with repeated use — diabetes, osteoporosis, and more — a genuine alternative could change daily life for millions of people who live in fear of the next flare-up. After a half-century of stalled progress on diseases that claim 3.8…
-

Mexico launches universal healthcare for all 133 million citizens
Mexico universal healthcare is now officially a reality, with the country launching a system designed to cover all 133 million citizens through the restructured IMSS-Bienestar network. Before this reform, an estimated 50 million Mexicans had no formal health insurance, with rural and Indigenous communities bearing the heaviest burden of untreated illness and medical debt. The new system severs the long-standing tie between employment and healthcare access, providing free consultations, medicines, and hospital services regardless of income. If implemented effectively, Mexico’s move could serve as a powerful model for other middle-income nations still navigating fragmented, inequitable health systems.

